4EkL9UN1tWH china.huanqiu.comgallery广州白云站项目建设有序推进 已进入装饰装修阶段/e3pmh1nnq/e3pn6eiep1696031004466责编:赵钰阳中国新闻网169603100446611[]{"audio":{"members":[]},"gallery":{"members":[{"desc":"中铁建工集团广州白云站项目是粤港澳大湾区的重点项目。为实现今年年底竣工的目标,该项目中秋、国庆“双节”期间不离岗不停工,超过300名职工、5000名工人自愿选择坚守岗位,超过900台大型作业车继续奋战在施工一线,奋力推进项目建设。承建单位中铁建工集团相关负责人介绍,中铁建工广州白云站项目目前已全面进入了室内外装饰装修阶段,站房整体金属屋面已完成90%,玻璃幕墙已完成80%,候车大厅已完成80%,光谷区域装修已完成50%,按照剩余工程的安排,预计2023年10月底完成大面积的装饰装修工程,2023年年底基本竣工。","height":393,"id":"022365f72d345bf73bd2cb85804c0987u5","mime":"image\/jpeg","size":83.21,"url":"//img.huanqiucdn.cn/dp/api/files\/imageDir\/022365f72d345bf73bd2cb85804c0987u5.jpg","width":700},{"desc":null,"height":393,"id":"92ee9e5f3f64df536b340cf2f42ee5ecu5","mime":"image\/jpeg","size":56.96,"url":"//img.huanqiucdn.cn/dp/api/files\/imageDir\/92ee9e5f3f64df536b340cf2f42ee5ecu5.jpg","width":700},{"desc":null,"height":393,"id":"a1d2a6efc7c87d69ee6f63fd331a7cd3u5","mime":"image\/jpeg","size":60.5,"url":"//img.huanqiucdn.cn/dp/api/files\/imageDir\/a1d2a6efc7c87d69ee6f63fd331a7cd3u5.jpg","width":700}]},"video":{"members":[]}}//img.huanqiucdn.cn/dp/api/files/image/bddc98267d491d340f369f385644454ac5.jpg